about this project
RS Contracting is moving along nicely with water main installation - they are finishing up with work on Emerald Dr this week (12/19/25). They will start on the west end of Falcon on Monday - 12/22/25 and Tuesday 12/23/25 and then break for Christmas. On Monday 12/29/25 - Wednesday 12/31/25 they plan to work on Falcon between Byrd and Connor Ln. Be prepared for temporary street closures on those streets. Contact the office if you have any questions 928-927-3088. Thank you for your patience during this long-awaited improvement to our water system!!